OnGoing Project's

Select Location




Project Name: SEL AFROZA MOTALIB SWAPNODHARA
Eskaton, Dhaka(Land: » 52katha.)
.||.
Address:Plot-90 & 91 New Eskaton Road, Ramna, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.122.34.360.16-369
Approval Date:Sunday, June 19, 2016
Construction Start Date:Saturday, October 01, 2016
Estimated Construction Period:52 Months. (approx.)

Project Details
No Of Building(s):3
Floor(s): 2B|G+14 G+13 G+13

Details of # B#: (1) & Name/Block: (A). B#: (2) & Name/Block: (B). B#: (3) & Name/Block: (C).
 TotalSaleableAvailable
.Flat391911
.Flat37185
.Flat39218


For current picture of this project, please           .

Project Name: SEL ANWAR ANGAN
Bara Maghbazar, Dhaka(Land: » 10katha.)
.||.
Address:38/1 Dilu Road, Bara Moghbazar, Ramna, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.122.33.222.19.351
Approval Date:Thursday, August 08, 2019
Construction Start Date:Friday, November 15, 2019
Estimated Construction Period:29 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1871


For current picture of this project, please           .

Project Name: SEL BHUIYAN PARK
Dhanmondi, Dhaka(Land: » 20katha.)
.||.
Address:Plot-13, Road-07, Dhanmondi
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.116.34.029.16
Approval Date:Monday, April 18, 2016
Construction Start Date:Friday, May 20, 2016
Estimated Construction Period:49 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 1B|G+12

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat35170


For current picture of this project, please           .

Project Name: SEL CHAYANEER
Mohakhali, Dhaka(Land: » 91katha.)
.||.
Address:Plot-KA/115/6/1, Dokkhinpara, Mohakhali, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:U:NI: 4/13C-388/15/451
Approval Date:Sunday, July 12, 2015
Construction Start Date:Monday, May 09, 2016
Estimated Construction Period:59 Months. (approx.)

Project Details
No Of Building(s):5
Floor(s): 1B|G+9 G+9 G+9 G+9 G+9

Details of # B#: (1) & Name/Block: (A). B#: (2) & Name/Block: (B). B#: (3) & Name/Block: (C). B#: (4) & Name/Block: (D). B#: (5) & Name/Block: (E).
 TotalSaleableAvailable
.Flat36158
.Flat362421
.Flat322118
.Flat341414
.Flat361212


For current picture of this project, please           .

Project Name: SEL CHOWDHURY VILLA
Aorangajeb Road, Dhaka(Land: » 12.5katha.)
.||.
Address:Plot-13/4, Block-A, Aorangajeb Road, Mohammadpur, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.098.33964.19
Approval Date:Tuesday, December 31, 2019
Construction Start Date:Saturday, January 25, 2020
Estimated Construction Period:34 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 1B|G+11

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat32135


For current picture of this project, please           .

Project Name: SEL CITY ARCADE
Dagarmura, Savar, Dhaka(Land: » 42.42katha.)
.||.
Address:Plot-1,Dagarmura, Savar Bus Stand, Savar
Project Type:Residential cum Commercial
Project Status:Ongoing
Approval:SAPOU/PROKOU/2015-2016/1245
Approval Date:Tuesday, February 02, 2016
Construction Start Date:Wednesday, April 27, 2016
Estimated Construction Period:69 Months. (approx.)

Project Details
No Of Building(s):2
Floor(s): 1B|G+13 1B|G+13

Details of # B#: (1) & Name/Block: (1). B#: (2) & Name/Block: (2).
 TotalSaleableAvailable
.Shop996
.Office404040
.Flat108108105


For current picture of this project, please           .

Project Name: SEL GOFRAN HERITAGE
Bashundhara (Block-H), Dhaka(Land: » 5katha.)
.||.
Address:Plot-367, Block-H, Bashundhara, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.106.33.675/17/912
Approval Date:Tuesday, October 10, 2017
Construction Start Date:Tuesday, April 17, 2018
Estimated Construction Period:28 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1151


For current picture of this project, please           .

Project Name: SEL JAHANARA ABDULLAH VILLA
Dilu Road, Dhaka(Land: » 7.35katha.)
.||.
Address:Holding No-48, Dilu Road, Maghbazar, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.122.33.544.18.788
Approval Date:Monday, December 31, 2018
Construction Start Date:Wednesday, May 22, 2019
Estimated Construction Period:27 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1883


For current picture of this project, please           .

Project Name: SEL JAHANARA FERDOUS RESIDENCE
Uttara (Sector-04), Dhaka(Land: » 5.41katha.)
.||.
Address:Plot-07, Road-06, Sector-04, Uttara R/A, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.000.090.33.289.19.88
Approval Date:Sunday, February 09, 2020
Construction Start Date:Sunday, March 08, 2020
Estimated Construction Period:24 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat833


For current picture of this project, please           .

Project Name: SEL KARNAFULI
Dhanmondi, Dhaka(Land: » 20katha.)
.||.
Address:Holding Number-08 (New), 19/A (Old), Road-06, Dhanmondi, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.116.34.229.19
Approval Date:Sunday, January 12, 2020
Construction Start Date:Thursday, May 16, 2019
Estimated Construction Period:41 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 2B|G+13

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat35140


For current picture of this project, please           .

Project Name: SEL LATIF HEIGHTS
Asad Avenue, Dhaka(Land: » 12.5katha.)
.||.
Address:Plot-3/10, Asad Avenue, Mohammadpur, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.098.33.965.19
Approval Date:Tuesday, December 31, 2019
Construction Start Date:Sunday, December 08, 2019
Estimated Construction Period:40 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 1B|G+13

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat331815


For current picture of this project, please           .

Project Name: SEL MANHA PARADISE
Bashundhara (Block-D), Dhaka(Land: » 10katha.)
.||.
Address:Plot-61 & 62, Road-04, Block-D, Bashundhara, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.106.33.158/19/672
Approval Date:Tuesday, August 20, 2019
Construction Start Date:Saturday, September 07, 2019
Estimated Construction Period:36 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 1B|G+13

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat251312


For current picture of this project, please           .

Project Name: SEL MAZUMDER CASTLE
Bashundhara (Block-F), Dhaka(Land: » 6katha.)
.||.
Address:Plot- 656 & 657, Block-F, Bashundhara, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.106.33.803/17-966
Approval Date:Thursday, November 02, 2017
Construction Start Date:Wednesday, February 14, 2018
Estimated Construction Period:26 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+7

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1372


For current picture of this project, please           .

Project Name: SEL MOSLEMINS VISTA
Humayoun Road, Dhaka(Land: » 6.03katha.)
.||.
Address:Plot-1/14, Block-B, Humayun Road, Mohammadpur, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.098.33.1069.16-253
Approval Date:Wednesday, February 28, 2018
Construction Start Date:Tuesday, February 28, 2017
Estimated Construction Period:44 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+7

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1460


For current picture of this project, please           .

Project Name: SEL NILOFAR VILLA
Elephant Road, Dhaka(Land: » 6.65katha.)
.||.
Address:288, Elephant Road, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:ZONE-5/25.39.0000.116.33.183.18/223
Approval Date:Tuesday, November 27, 2018
Construction Start Date:Friday, December 28, 2018
Estimated Construction Period:25 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+8

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1460


For current picture of this project, please           .

Project Name: SEL NIRALA BHABAN
zigatola, Dhaka(Land: » 15.3katha.)
.||.
Address:Plot-300/2 & 300/3 Sher E Bangla Road, Tollabagh, Zigatola, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:ZONE- 5/25.39.0000.116.33.254.18/15
Approval Date:Tuesday, February 12, 2019
Construction Start Date:Thursday, September 19, 2019
Estimated Construction Period:30 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 1B|G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat402013


For current picture of this project, please           .

Project Name: SEL NIRALA KUTIR
Free School Street, Dhaka(Land: » 25.96katha.)
.||.
Address:397 Free School Street, Hatirpool, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:ZONE-5/25.39.0000.116.33.086.19/123 STHA
Approval Date:Wednesday, July 10, 2019
Construction Start Date:Friday, September 06, 2019
Estimated Construction Period:34 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 1B|G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat62317


For current picture of this project, please           .

Project Name: SEL NOORJAHAN TOWER
New Eskaton, Dhaka(Land: » 12.95katha.)
.||.
Address:PLOT-02, NEW ESKATON, RAMNA, DHAKA
Project Type:Commercial
Project Status:Ongoing
Approval:25.39.0000.122.33.194.18.539
Approval Date:Thursday, September 13, 2018
Construction Start Date:Sunday, September 08, 2019
Estimated Construction Period:41 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): 2B|G+13

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Shop555
.Office341919


For current picture of this project, please           .

Project Name: SEL REZIA MALEK
Bagichagaon, Cumilla(Land: » 8.48katha.)
.||.
Address:Plot-112, Bagichagaon, cumilla
Project Type:Residential
Project Status:Ongoing
Approval:KUSIK/PRKOU:B:/774/29-9-2016/1309
Approval Date:Thursday, August 10, 2017
Construction Start Date:Saturday, July 15, 2017
Estimated Construction Period:37 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+8

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat32207


For current picture of this project, please           .

Project Name: SEL ROWSHALI
Banani (Block-I), Dhaka(Land: » 7.75katha.)
.||.
Address:Plot-33, Road-1/A, Block-I, Banani, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.106.34.250/19/691
Approval Date:Sunday, September 01, 2019
Construction Start Date:Tuesday, July 16, 2019
Estimated Construction Period:28 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+7

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat1476


For current picture of this project, please           .

Project Name: SEL SEPIA TONES
(Block-B), Bashundhara, Dhaka(Land: » 5katha.)
.||.
Address:Plot-57, Road- 9, Block-B, Bashundhara, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.106.33.612/18/922
Approval Date:Tuesday, October 02, 2018
Construction Start Date:Monday, February 18, 2019
Estimated Construction Period:27 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat953


For current picture of this project, please           .

Project Name: SEL SHORNALI
Banani (Block-F), Dhaka(Land: » 5.47katha.)
.||.
Address:House-8, ROAD-2/A, BLOCK-F, BANANI, DHAKA
Project Type:Residential
Project Status:Ongoing
Approval:25.39000010634.489/18/716
Approval Date:Monday, July 23, 2018
Construction Start Date:Saturday, November 17, 2018
Estimated Construction Period:26 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat840


For current picture of this project, please           .

Project Name: SEL WATER LILY
Bashundhara (Block-A), Dhaka(Land: » 5katha.)
.||.
Address:Plot-60, Block-A, Bashundhara, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:25.39.0000.106.33.814/18/1098
Approval Date:Sunday, November 25, 2018
Construction Start Date:Thursday, April 11, 2019
Estimated Construction Period:28 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat843


For current picture of this project, please           .

Project Name: SEL ZAMAN HERITAGE
Indira Road, Dhaka(Land: » 5.3katha.)
.||.
Address:47/13 West Rajabazar, Indira Road, Dhaka
Project Type:Residential
Project Status:Ongoing
Approval:ZONE-5/25.39.0000.116.33.100.18-103STHA
Approval Date:Tuesday, June 12, 2018
Construction Start Date:Wednesday, December 12, 2018
Estimated Construction Period:25 Months. (approx.)

Project Details
No Of Building(s):1
Floor(s): G+9

Details of # B#: (1) & Name/Block: (1).
 TotalSaleableAvailable
.Flat950


For current picture of this project, please           .